| Minimum Frequency
of Tests |
| OPERATOR |
MIN. # OF TIMES |
STAGES |
| Inspection |
4 |
Rec, Pre-HF,
Post-HF, Final |
| Pressure
Test |
9 |
Several Stages |
| Dye Penetrant
Test |
6 |
Pre-Weld,
Pre-HT, Pre-HF, Post-HP, Pre-Grind |
| Hardness
Test |
6 |
Rec, Pre-HT,
Pre-HF, Post-HT,
Pre-HF, Post-HF, Pre-Grind |
GEMCO maintains a HISTORICAL DATA FILE on each Job
sent to us - REGARDLESS OF PRODUCT.
Continually monitoring operations, materials, technology
etc. throughout the years, we continue to gain experience
and knowledge amending operations accordingly to insure
Quality Products.
Our tenured Craftsmen, 20 + years at GEMCO, are committed
to providing a Quality Product and Service.
OUR QUALITY CONTROL AND ASSURANCE
PROGRAM IS BASED ON THE ISO 9001 GUIDELINES.
QC&A is carried out in three stages.
Inspection and Testing of Incoming Materials.
In-process Inspection and Testing.
Inspection and Testing of Finished Product.
Different Inspection Reports and Checklists are used
extensively, as tools, to assist in the successful implementation
of the applicable Inspection Plan.
Reports are used at Specific Stages of manufacturing.
This ensures that only Conforming Products are released
for use.
Only personnel trained in specific operations are authorized
to undertake those specific tasks.
THE PURPOSE OF GEMCO'S QC&A
PROGRAM IS TO ENSURE THAT ALL
GOODS AND SERVICES CONFORM TO THE APPLICABLE STANDARDS,
AS WELL AS THE SPECIFICATIONS ESTABLISHED BY THE
CUSTOMER. |
|